Project Cost:>HK$10M
Peak ESL Team Size:75
Project Duration:40 months

ESL provided construction support services during the excavation, ELS work and lower structure.

The major part of this project is the excavation and lateral support followed by piling and construction of the structure for the largest part of the West Kowloon Terminus.

Survey work included excavation recording, volume calculation and monitoring during the initial phase followed by set out of major grids/datumsĀ  and detailed set out where required.

Back to projects list